33. A contract is to be completed in 46 days and 117 men were set to work,
each working 8 hours a day. After 33 days, 4/7 of the work is completed.
How many additional men may be employed so that the work may be completed
in time, each man now working 9 hours a day?
Answer:
4/7 of work is completed .
Remaining work=1- 4/7
=3/7
Remaining period= 46-33
=13 days
Less work, less men(direct proportion)
less days, more men(Indirect proportion)
More hours/day, less men(Indirect proportion)
work 4/7:3/7
Days 13:33 :: 117:x
hrs/day 9:8
(4/7)*13*9*x=(3/7)*33*8*117
x=(3*33*8*117) / (4*13*9)
x=198 men
So, additional men to be employed=198 -117=81