65. 36 men can complete a piece of work in 18 days. In how many days will 27 men complete the same work?
A. 12 B. 18
C. 22 D. 24
E. None of these
Answer: Option D
Explanation:
Let the required number of days be x.
Less men, More days (Indirect Proportion)